COVERED GREEN INITITAIVE UPDATE as at 03 Dec 2025
The council has advised the following:
- Canopy Drawings commence and are to be submitted to Planning Department for approval in accordance with Permit Approval Conditions
- 15 March 2026 Civil Works commence (duration 3-4 weeks)
- Canopy Construction 27 April to 5 June
- Install of Green (duration 2-3 weeks)
There are still details to work through and when these have been completed, I will hold a meeting to discuss the project in detail.
Mal Shield